Post Construction Inspections Workflow Overview

1. Run the "Prep For Post Construction" tool

 

2. Collect data in the field
3. Continue like normal with photo upload, classification, and association
4. After photo association, run the "PCI Routine" tool to calibrate photos
5. Once calibration is acceptable, transfer heights
6. If any attachments are misaligned with the height of their marker (where the attachment doesn't appear where it should be), move the marker where its attachment actually is
7. Now you can call new Make Ready to fix any new violations on this pole
8. Move on to the next pole or click "Exit View" once you are done performing calibration and necessary Make Ready calls

 

For more detailed instructions on how to use our Post Construction Inspection tools in our software, check out our Post Construction Inspections Manual.